Normal_left_montage_imageNormal_middle_montage_imageNormal_right_montage_image
cathedral commons john instagram

Cathedral Commons: June 2014 Construction Update

Post by Cathedral Commons. (Continue reading)

Welcome to the Neighborhood: Meet the First Seven Retailers Joining Cathedral Commons

We’re very excited to welcome the following seven retailers to the Cathedral Commons community: Barcelona Restaurant & Wine Bar, Raku, iDoc Optical, Wells Fargo, SunTrust, CVS Pharmacy, and Starbucks. Retail is slated to begin opening this fall alongside the 56,000-square-foot Giant Food, which will bring a new urban prototype concept to its state of the art lifestyle… (Continue reading)

Cathedral Commons Construction Update [PHOTO]

Post by The Bozzuto Group. (Continue reading)

Constr12.13_2

Cathedral Commons Construction Update

December 9, 2013
By
No Comments
Cathedral Commons

Concrete has completed on the South Parcel. Load bearing walls have been installed for the residential units. We are in the process of installing steel throughout the Giant retail space. Tower Crane number 1 will be taken down on 11/25/13. Our first pour of the 2nd floor of the North Parcel took place on 11/21/13…. (Continue reading)

Cathedral Commons Construction

July Cathedral Commons Construction Update

Concrete will continue on the South Parcel. We have begun to frame the first elevated deck slab! The tower crane on the North Parcel is schedule to be installed in the next couple of weeks. It will be the tallest of three tower cranes on this project. We are also planning to close Idaho Avenue,… (Continue reading)

cathedral commons construction site

Cathedral Commons Construction and Excavation Update

We’re kicking off the month of May with a continuation of the mass excavation, which will likely be completed by the end of the month. Concrete began on April 22 with the installation of the first tower crane on the South Parcel. Street Closure information: We will close Idaho Avenue, between Newark Street and Macomb Street,… (Continue reading)

South site construction at Cathedral Commons

Spring Construction Update at Cathedral Commons

Mass excavation will continue through approximately the middle of May. As of now, the excavation is 60% complete. Concrete is scheduled to begin around mid-April with the installation of the first tower crane on the South Parcel. We are also still planning to close Idaho Avenue, between Newark Street and Macomb Street, for utility work… (Continue reading)

cc

Excavation Continues at Cathedral Commons

The driving of piles is complete for the support of excavation. Mass excavation will continue through approximately the middle of May. We are still planning to close Idaho Avenue, between Newark Street and Wisconsin Avenue, for utility work from approximately the middle of April to the end of May. We will give the specific dates… (Continue reading)

cc3

Construction Update at Cathedral Commons

February 7, 2013
By
No Comments
Cathedral Commons, Washington DC, Washington DC NW

The support of excavation is going according to schedule and should be completed by April. The mass excavation is also going as scheduled and it will continue for the next few months. An important update: we are planning to close Idaho Avenue, between Newark Street and Wisconsin Avenue, for utility work from approximately the middle… (Continue reading)

cathedral

Cathedral Commons Construction Update

January 18, 2013
By
No Comments
Cathedral Commons, Washington DC, Washington DC NW

The Support of Excavation (pile driving) is nearly 90% complete on the South Parcel and has moved onto the North Parcel. Mass Excavation has begun on the South Parcel and will continue for the next few months. The Newark Street closure occurred on January 7, under DDOT supervision. We are working with DDOT and the… (Continue reading)